Complete

Project Value £4.5m GBP (Approx)

Refurbishment

Project Overview:

APV Building Refurbishment Project. Works consisted of, installation of a new lift shaft, strip out and overhaul of APV Building, to include the following elements; M&E refurbishment, glazing refurbishment, construction and fit out of new WC’s, finishing works, cladding works and civil engineering works (Lift Pit Works). These works were done to accommodate four new gates for Ryanair use.

*Refurbishment Project Quantity surveying and Estimating Services

KEY FEATURES :

Naboh Cost Engineering were responsible for:

Procurement of subcontractors,

Contract administration,

Subcontract management,

Subcontract payments, Agreeing Compensation Events,

Record keeping,

Monthly Liability Reporting.

Monthly Cost and Value Reporting.

Project involved multiple subcontractors and various works packages.

NEC 3 Option A Contract